Phase 2C Groundbreaking in West Concord on Friday, July 14th

ground-breaking-photo

Come help us celebrate! On Friday, July 14th, 2017 at 1:00 PM, the Massachusetts Department of Transportation will join officials from the town of Concord and  the Friends of the Bruce Freeman Rail Trail to celebrate a groundbreaking event for Phase 2C

Posted in Trail Events, Trail News, Trail Status

Rt 2A Bridge Work in Acton

Rt 2A Bridge in Acton, Massachuesetts

Early in June, the Route 2A bridge was painted to look like natural stone. This photo shows the contrast between the “primed” rockface wall and a finished section. The primer coat turns the gray wall a pearly ivory color. The

Posted in Trail News, Trail Status

Sudbury: Rail trail officially in pipeline for construction funds

SUDBURY – Decades later, the Bruce Freeman Rail Trail is another step closer to reality. A regional planning body on Thursday placed the project in the queue to receive $8 million in state and federal construction money in fiscal 2022.

Posted in Trail News, Trail Status

April 26, 2017 – Please Attend continued Conservation Commission hearing re: Gervais VW

The Bruce Freeman Rail Trail near Lowell.

Please support the Rail Trail in Lowell This meeting is now to be continued on April 26th, 2017. Gervais VW purchased the BFRT ROW just north of Industrial Ave (and Crosspoint) from PanAm Railways.  Gervais wants to expand parking onto

Posted in Trail News, Trail Status, Volunteer Opportunities

April 23, 2017 – Phase 2C Construction Update

IMG_1999

Construction starts on Phase 2C in Concord in May. Stay tuned as we post more updates in the next few weeks.

Posted in Trail News, Trail Status

March 22, 2017 – Please Attend Conservation Commission Meeting re: Gervais VW

Summer Solstice Ride on the Bruce Freeman Rail Trail - June 21, 2014

Please support the Rail Trail in Lowell Gervais VW purchased the BFRT ROW just north of Industrial Ave (and Crosspoint) from PanAm Railways.  Gervais wants to expand parking onto the ROW.  There may be a way for the BFRT to

Posted in Trail News, Trail Status, Volunteer Opportunities

02/12/2017 – See Panoramic Images of the Bruce Freeman Rail Trail

A view of the bridge from Rte 2A - Photo: Larry Bruns

Here is a link to a panoramic image of the new bridge crossing route 2A. Click on the image or the link to go to the www.360cities.net website to view this panoramic photograph taken by Concord resident John Wood. There

Posted in Trail News, Trail Status

12/31/2016 – Bruce Freeman Year End Appeal. Bridge the Phase 2B Gap

20161114-bridge-day-lb

IMPORTANT UPDATE 02/05/2017:  The state has decided to step up and fund the remaining $350K of the design work.  Please stay tuned for additional information on this exciting development.  At this time the FBFRT have suspended the Bridge the Gap campaign and

Posted in Trail News, Trail Status, Volunteer Opportunities

December 19, 2016 – Thanks for your support – 2016 in Review

Bridge over Nashoba Brook in West Concord - December 2016

We are very pleased with the significant progress made on the rail trail this past year. The contract for construction of Phase 2C through West Concord has been awarded! We anticipate that groundbreaking will be held in early 2017. Construction

Tagged with: ,
Posted in Trail News, Trail Status

December 1, 2016 – News about Construction Bid Package for Phase 2C in Concord

Phase 2C - Concord, MA

The construction bid package for the Bruce Freeman Rail Trail Phase 2C project was advertised; bids were opened on Tuesday, November 29, 2016. The apparent low bidder is D.W. White at $6,709,393.74. Contract negotiations  are expected to begin shortly. For

Posted in Trail News, Trail Status