Concord Town Meeting begins on Sunday, May 4, 2014 Article 39 Article 39 is on the Town Meeting warrant by petition. It calls for additional studies that would duplicate work already completed or planned in the normal course of…
Concord Town Meeting begins on Sunday, May 4, 2014 Article 39 Article 39 is on the Town Meeting warrant by petition. It calls for additional studies that would duplicate work already completed or planned in the normal course of…
While Phase 2A is near the end of its design, Phase 2B – primarily the crossing over Route 2 – is still in the preliminary (25%) design stage. Four bridge type selection reports have been submitted to MassDOT by consultant…
“A $950,000 Gateway City Parks grant and a $400,000 Parkland Acquisitions and Renovations for Communities, or PARC, grant will finance the last two stretches of the park that runs along the Concord River, joining it with the longer Bay Circuit…
It has been one step back and two steps forward for the Phase 2A design. The step back, a realignment of the Rt. 2A (Great Road) bridge, is an interesting one that we believe will be worth the wait. The…
Almost $24 million in construction funds for Phases 2A, 2B, and 2C have been recommended by the Boston Metropolitan Planning Organization (MPO) over the next four years. The Draft 2014-2017 Transportation Improvement Program (TIP) released in May for public comment…