May 12, 2022 – Phase 2B (Bridge over Route 2) Update

Phase 2B Update: The contractor has submitted a request to extend the completion date to November 30, 2022 due to the scheduling of weather-dependent activities. The staining and application of anti-graffiti material will take place later in May; the staining will take 3-4 weeks, will cure for 8 days and then the anti-graffiti material will be applied, which will be at the end of June. The planting season ends in June, so the planting schedule has been extended to the fall (late September/October/early November). Additionally, the top course of paving is expected to be done in July.

Monthly construction updates from the Town of Concord are available here:
https://www.concordma.gov/1830/Monthly-Updates  