Sudbury Board of Selectman Candidates Responses

Sudbury Voters and Interested Parties, The Board Friends of the Bruce Freeman Rail Trail (FBFRT) decided to ask the Sudbury Board of Selectmen (BOS) candidates for the June 25, 2013 special election two very specific questions to elicit their stance

Tagged with:

Next 3 Phases of the Trail Recommended for Construction!

Almost $24 million in construction funds for Phases 2A, 2B, and 2C have been recommended by the Boston Metropolitan Planning Organization (MPO) over the next four years. The Draft 2014-2017 Transportation Improvement Program (TIP) released in May for public comment

Tagged with: , ,

Phase 2 Update Concord

Two portions of Phase 2 of the rail trail are entirely or mostly in Concord: the crossing of Route 2 from Acton to Concord (Phase 2B) and the main portion of the trail through West Concord to the Concord/Sudbury town

November 2012 Update | Phase 2 Westford, Carlisle, Acton

In late October 2012 the 75% design plans for Phase 2A (Westford, Carlisle, and Acton), thus adhering to the schedule for the project to be advertised for construction in fiscal year 2014. The bulk of the work was completed by

2012 Rail Trail Counts

Trail count information from May and September is now available. Many thanks to all who volunteered for this event. Details Here

Fence Openings, Chelmsford, MA

Thanks to Ken Dews, FBFRT member and volunteer, direct access is now available from the BFRT to Zesty’s Pizza, Subway sandwich shop, and neighboring businesses. Two handicapped-accessible openings were installed in June. A big thank-you to Ken and to those