Construction Info

Rail Trail Construction FAQ is available here

For Chelmsford status and questions contact Cynthia McLain

For Westford status contact Emily Teller

Phase 1 Memorandum of Agreement details here.

Amenities and Acquistions

The Friends of the BFRT are assisting with amenities, such as benches and bike racks, and the acquisition of the Phase 3 portion of the railroad right of way (ROW). The rail trail will also need regular maintenance for which the Friends will provide support. More information here

RAILs, TRAILs and TIES

This column in the Chelmsford Independent has information about the current progress on the trail.

September 18, 2008 - Work on Freeman Rail Trail rolls along

September 4, 2008 - Keeping track of the bicycle trail

July 3, 2008 - Rail trail construction shifts to the Center

June 5, 2008 - New bicycle and pedestrian committee

April 24, 2008 - Where will the rail trail run?

March 6, 2008 - A real count of potential trail users
Topic: Statewide trail usage counts on Sept. 8, 2007

January 17, 2008 - Clearing of the rail trail completed
Topic: Phase 1 construction

December 26, 2007 - Greenway slated for rail trail
Topic: Concord River Greenway and Greenway Connector Trail

December 12, 2007 - Many components to rail trail
Topic: Bruce Freeman Rail Trail Coordinating Committee

November 20, 2007 - Work on the bike trail has started
Topic: Phase 1 construction

September 26, 2007 - Bike trail groundbreaking set
Topic: Brief history of Phase 1

September 20, 2007 - New Column
Topic: Phase 1 construction

Related Links

History of the Railway in Chelmsford Details Here

Chelmsford Land Conservation Trust http://www.clct.org/

Chelmsford Historical Society http://www.chelmhist.org/

Lowell Parks and Conservation Trust http://lowelllandtrust.org/

Middlesex Canal Association http://www.middlesexcanal.org/

 


PHASE 1 Construction Information

Overview

The trail is currently closed to use.

Construction is anticipated to be complete in summer 2009. The section of trail under construction extends from the Lowell/Chelmsford line near Cross Point, through Chelmsford Center, to the intersection of Route 27 and Route 225 in Westford.

Please stay off the rail trail corridor during construction, to avoid injury from equipment, debris, and other hazards created by the construction process. Heavy equipment is used during construction and the entire rail corridor is considered a work zone.

In August 2008, installation of the trail base began at Route 3 in Chelmsford and is proceeding south. Construction work will be evident in Chelmsford Center during September and October. Work may not be evident along Route 27 until spring 2009, depending on the length of the construction season as determined by winter weather.

Curbing for the rail trail has been installed between the parking lots in the rear of Village Square and 30 Chelmsford St. (Chelmsford Cyclery) to 60 Chelmsford St. (Highlights Salon). Installation of curbing in other areas in Chelmsford Center will wait until 2009 in deference to abutting businesses.

Curbing and railings for the 4 bridges will be installed once the risk of damage from other construction activity is past.

Answers to Frequently Asked Questions (FAQs) about Rail Trail Construction are available here.

9/30/2008
Current Project Status

Erosion Control fence installation completed.
Clearing operation is complete. (January 7, 2008)
Track Removal is complete.
Bridge Demolition on 4 of the 4 bridges complete.
Track Timber Tie removal is complete.
Beam placement on all four bridge complete.
Pre and Post tensioning of bridge beams complete
Wingwalls and backwalls on all four bridge complete.
Drainage system installations at all locations complete.
Granite curb installation at 60 Chelmsford St. area is complete.
Preliminary excavation and grading began on August 11, 2008 at the Route 3 end of project.
Grading is complete from Rt. 3 to Center of Chelmsford (September 30, 2008)

Additional Information

Grading will continue from behind Bertucci’s towards High St. during the next two weeks.
Other areas to be excavated and graded will commence shortly thereafter.

Construction Update Archive

Construction Benchmarks

Apr 2007 Phase 1 advertised for construction bids

Jun 2007 Construction bids opened

Aug 2007 Notice to Proceed issued

Aug 2007 Preconstruction meeting

Oct 2007 Groundbreaking ceremony

Dec 2007 Erosion control installation completed

Jan 2008 Clearing of trees and undergrowth from rail bed completed

Mar 2008 Track removal completed

May 2008 Tie removal completed

Jun 2008 Drainage system installation complete

Jul 2008 Granite curbing installation at Village Sq. and 30-60
Chelmsford St. completed

Please see the MassHighway project web site for status and contact information.

The number for the answering machine in the Resident Engineer's field office is 978-256-3947. Please leave the following information: name, daytime phone number, address (for abutters), email address (optional), and a one or two sentence description of the reason for the call.

An email address will lead to a quicker initial response. We will research the question and get back to you. We ask that you review the information on the website before calling.

While waiting for a response, please keep in mind that the Resident Engineer is working on multiple projects.